Project Status

CONSTRUCTION UPDATE-08.11.2018

Tower-5-Structure Works

  • Foundation works completed up to EGL-100%
    • All Footing with pedestal column casting completed & Column casting at Stilt floor
  • Structure Works in upper floors
Floor Columns Roof cast Blockwork Wall plaster Ceiling plaster Water proofing Exter plaster
First floor 100% 100% 95% 98% 99% 20% 90%
Second floor 100% 100% 95% 98% 99% 97%
Third Floor 100% 100% 95% 98% 99% 97%
Fourth floor 100% 100% 95% 98% 99% 97%
Fifth floor 100% 100% 95% 98% 99% 67%
Sixth floor 100% 100% 95% 98% 99% 6%
Seventh floor 100% 100% 95% 98% 99% 6%
Eighth floor 100% 100% 95% 49% 99% 6%
Nineth floor 100% 100% 79% 59% 6%