Project Status

CONSTRUCTION UPDATE-09.07.2018

Tower-5-Structure Works

  • Foundation works completed up to EGL-100%
    • All Footing with pedestal column casting completed & Column casting at Stilt floor
  • Structure Works in upper floors
Floor Columns Roof cast Blockwork Wall plaster Ceiling plaster Water proofing Exter plaster
First floor 100% 100% 95% 95% 100% 20% 10%
Second floor 100% 100% 95% 95% 100%
Third Floor 100% 100% 95% 90% 95%
Fourth floor 100% 100% 95% 90% 90%
Fifth floor 100% 100% 95% 80% 90%
Sixth floor 100% 100% 95%
Seventh floor 100% 100% 70%
Eighth floor 100% 100% 20%
Nineth floor 100%