ENQUIRE WITH US

Project Status

CONSTRUCTION UPDATE-06.04.2018

Tower-5-Structure Works

  • Foundation works completed up to EGL-100%
    • All Footing with pedestal column casting completed & Column casting at Stilt floor
  • Structure Works in upper floors
Floor Columns Roof cast Blockwork Wall plaster Ceiling plaster Water proofing Exter plaster
First floor 100% 100% 95% 95% 100% 20% 5%
Second floor 100% 100% 95% 95% 100%
Third Floor 100% 100% 95% 40% 95%
Fourth floor 100% 100% 70%
Fifth floor 100% 100% 70%
Sixth floor 100% 100% 20%
Seventh floor 100% 100%
Eighth floor 100% 50%
Nineth floor
All Rights Reserved, XS Real
Top