CONSTRUCTION UPDATE-04.12.2017

Tower -5-Structure Works

  • Foundation works completed up to EGL-100%
    • A. Footing with pedestal column casting completed
    • B. Backfilling up to EGL completed
    • C. Plinth beam at EGL -100%
    • D. Column casting at Stilt floor
  • Structure Works in upper floor
Floor Column casting Slab casting Blockwork Internal Plastering External Plastering
First floor 100 % 100 % 70 %
Second floor 100 % 100 %
Third Floor 100 % 100 %
Fourth floor 100 % 100 %
Fifth floor 100 % 100 %
Sixth floor
Seventh floor